Project Update
July 16, 2008
During the
week of July 14th, concrete work will be finished and
restoration work will begin on the terraces. The placement of
base course and fine grading will be completed the week of July
21st with final asphalt to follow. The storm water
project at 3rd Avenue has been completed and will be
paved along with the rest of 2nd Street. Due to the
amount of rain received in June the contractor has a requested
an extension on the completion date. The new final completion
date for the project will be July 29,2008. The Village
appreciates your patience during this project. Thank-you.
Crews will be working daily
between 7:00 a.m. and 7:00 p.m.; if you have a driveway off 2nd
Street you may not have immediate access to your driveway
between these hours. Residents are encouraged to park on
side streets as much as possible. In addition, due to wet
weather it may be in your best interest to avoid driving on 2nd
Street, especially if you do not have a 4-wheel-drive vehicle.
Contractor
Huml
Contractors, Inc. of Janesville, Wisconsin, will be the
contractors on the 2008 2nd Street Reconstruction Project.
Engineer
Strand Associates,
Inc. of Madison, Wisconsin, will be the engineering firm
responsible for the 2008 2nd Street Reconstruction Project.
Notices
Project Plan
The
2008 Street Project includes the reconstruction of 2nd Street
between 6th Avenue and 11th Avenue. New curb & gutter,
road base coarse, and road asphalt will be installed. The
utilities will be upgraded including new sanitary sewer and
laterals between 6th Ave. and 11th Ave., new storm sewer between
6th Ave. and 11th Ave., and new watermain and laterals between
10th Ave. and 11th. Ave. ADA sidewalk ramps will be
installed along with spot sidewalk installation and replacement.
Schedule
Substantial completion of the project is planned for late
July 2008.
|
|