|
|
Contractor
C.D. Smith Construction of
Fond du Lac, Wisconsin, will be the
contractors on the WWTP Expansion Project.
Engineer
Strand Associates,
Inc. of Madison, Wisconsin, will be the engineering firm
responsible for the 2008 2nd Street Reconstruction Project.
Existing Plant
 |
|
 |
|
Influent Pumping Station
Wastewater is pumped from the influent pumping station
up to the treatment processes. The existing pumps
will be replaced to accommodate higher future wastewater
flows. |
|
Sludge
Pumping & Screening Building
The wastewater screen removes material from the
wastewater that may harm downstream equipment. The
existing wastewater screen will be moved to a new
screening building. |
| |
|
|
 |
|
 |
|
Biosolids Tank No. 2
Biosolids created from the wastewater treatment process
are stored in Biosolids Tank No. 2 (and Tank No. 1).
A new biosolids mixer will be place in Tank No. 2. |
|
Oxidation Ditch & Final Clarifier
The oxidation ditch and final clarifier treat the
wastewater. Each of these structures will be
upgraded. In addition, a second oxidation ditch
and second final clarifier will be constructed. |
| |
|
|
 |
|
 |
|
Cascading Aerator
Oxygen is entrained in the treatment plant effluent at
this structure just prior to discharge to the Little
Sugar River. A new flow meter will be installed at this
structure. |
|
Chemical Feed Building
This building houses a chemical storage tank and pumps
to help remove phosphorus from the wastewater.
Minor improvements will be done in this building. |
| |
|
|
Notices
- May 20, 2008 - Public Hearing - Sewer Rate Increase
Project Plan
Click
here for a Schematic of the Proposed Expanded WWTP.
Schedule
Currently, construction is expected to
start Late Spring/Early Summer 2008. Construction will be
completed Fall 2009.
|
|